[171212] in Hotline Meeting
Bldg. W20 - Basement Chilled Water Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Aug 1 10:09:05 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sudy@MIT.EDU>
Date: Thu, 1 Aug 2013 10:08:40 -0400
Message-ID: <55D08FEF6CE048A2A84151A26A976EA4@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Chilled Water Shutdown is for bldg. W20 - basement on Tuesday, August 6, 2013 from 2:00am - 6:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: August 5, 2013
Day: Tuesday
Time: 2:00am - 6:00am
Building(s): W20
Room(s): basement
System: chilled water
Duration: 2:00am - 6:00am 4 hrs
Reason:
We request a bldg W20-basement chilled water shutdown from 2 AM to 6 AM on Tuesday morning, August 6th, 2013 for cutting in new valves of the chilled water branch line as part of the W20-019 catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). Sudy Nally 8-8010 and Jason Mullen 4-7232 are the MIT project managers on behalf of Billy Homeyer.
Effect:
Loss of chilled water for the duration of this shutdown.