[171193] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg.1-Yard Main Fire Protection Water Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jul 31 12:11:54 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jwestgat@MIT.EDU>, <healyb@MIT.EDU>
Date: Wed, 31 Jul 2013 12:11:47 -0400
Message-ID: <A609123E7C524BE29ABC4C64162CB5F4@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Protection Water, shutdown notification for Bldg.1-Yard Main on Thursday, August 1, 2013 (into Friday morning) from 10:00pm-6:00am is for your information. No response required to this notification. Any question please contact Billy Homeyer 8-0432. 

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Jessica Westgate
Operations Center
	
The Safety Office will be advised of this and notify the Fire Department.

Type: Normal
Date: August 1, 2013
Day: Thursday
Time: 10:00pm-6:00am
Building(s): 1
Room(s): Yard Main
System: Fire Protection Water
Duration: 8 hours
Reason: 
To replace existing gate valve in Killen Court area with a PIV.

Effect: 
Loss of fire protection water in area during the duration of the shutdown.

home help back first fref pref prev next nref lref last post