Approved Bldg. 32 - Stairwell Pressurization Systeam and Dreyfoos

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jul 30 13:09:21 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "mwf@mit.edu" <mwf@mit.edu>, "liscott@mit.edu" <liscott@mit.edu>,
        "pwalsh@mit.edu" <pwalsh@mit.edu>,
        "Kelley.kennedy@compass-USA.com"
	<Kelley.kennedy@compass-USA.com>,
        "myersm@MIT.EDU" <myersm@mit.edu>,
        "jackc@csail.mit.edu" <jackc@csail.mit.edu>,
        "jon@csail.mit.edu"
	<jon@csail.mit.edu>,
        "steverug@CSAIL.MIT.EDU" <steverug@csail.mit.edu>,
        "lizaz@CSAIL.MIT.EDU" <lizaz@csail.mit.edu>,
        "zue@csail.mit.edu"
	<zue@csail.mit.edu>,
        "isabell@mit.edu" <isabell@mit.edu>,
        "sbleeb@mit.edu"
	<sbleeb@mit.edu>,
        Michael Fahie <mfahie@plant.mit.edu>,
        "OPS RM Campus
 Services Main" <rm-mcs@mit.edu>,
        "Martin O'Brien" <mobrien@plant.mit.edu>,
        "Stata-Custodial@mit.edu" <Stata-Custodial@mit.edu>,
        Ops CSG All
	<csg-all@mit.edu>, "dwright@MIT.EDU" <dwright@mit.edu>,
        "stata-desk@mit.edu"
	<stata-desk@mit.edu>,
        "conferences-www@mit.edu" <conferences-www@mit.edu>,
        "scheruku@MIT.EDU" <scheruku@mit.edu>,
        "dgeraci@mit.edu" <dgeraci@mit.edu>, "rosko@mit.edu" <rosko@mit.edu>,
        Michael Smith <masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
        "awolpert@mit.edu" <awolpert@mit.edu>, "edel@mit.edu" <edel@mit.edu>,
        "shanlon@mit.edu" <shanlon@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "lrbrutti@mit.edu" <lrbrutti@mit.edu>, "rcruz@mit.edu" <rcruz@mit.edu>,
        "aneely@mit.edu" <aneely@mit.edu>, "wayneb@mit.edu" <wayneb@mit.edu>,
        MIT Schedules Office <schedules@mit.edu>,
        "k_brown@MIT.EDU" <k_brown@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "kdonaher@mit.edu" <kdonaher@mit.edu>,
        "kasabula@mit.edu" <kasabula@mit.edu>,
        "rpittari@mit.edu" <rpittari@mit.edu>,
        "ksimons@mit.edu" <ksimons@mit.edu>,
        "rwong@brighthorizons.com" <rwong@brighthorizons.com>,
        "worklife@mit.edu"
	<worklife@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        Karen Semerjian
	<ksemerj@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "kdiggans@mit.edu" <kdiggans@mit.edu>
Date: Tue, 30 Jul 2013 13:09:09 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C64FDD86@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved supply fan 8 and 8A and air conditioning unit for Bldg. 32 - Stairwell Pressurization Systeam and Dreyfoos Elevator Machine Room, on Wednesday, July 31, 2013, 6:00am - 2:00pm, is for your information.  Any questions, please contact Keith Diggans, 4-6174.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: July 31, 2013
Day: Wednesday
Time: 6:00am - 2:00pm
Building(s): 32
Room(s): Stairwell Pressurization Systeam and Dreyfoos Elevator Machine Room
System: Supply Fan 8, 8A, and ACCU
Duration: 8 hours
Reason: 
We request bldg 32-SF8A, SF8 & ACCU (Dreyfoos elevator machine room AC) shutdowns from 6 AM to 2 PM on Wednesday, July 31st, 2013 to power fans (breakers are locked out) to install permanent power to equipment & disconnect and to remove old temporary power (NOTE: may need to put fans in machine room to move air so equipment does not overheat) as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-509-2935), WEH for Keith Diggans 4-6174

Effect: 
Loss of Dreyfoos stairwell pressurization and elevator machine room supply ventilation for the duration of the shutdown.