[171117] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 32 - Dreyfoos Floors 4 through 9, Air Handler 2 (and chilled water to the air handler) Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 29 13:41:42 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggans@MIT.EDU>
Date: Mon, 29 Jul 2013 13:41:30 -0400
Message-ID: <8A28BD9D54204C8F86600F809972C44A@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following air handler 2 (and chilled water to the air handler) shutdown request for Bldg. 32 - Dreyfoos, Floors 4 through 9, on Saturday, August 3, 2013, 6:00am - 2:00pm, is for your information and response.  Any questions, please contact Karen Semerjian, x3-6217.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: August 3, 2013
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 32
Room(s): Dreyfoos, Floors 4 through 9
System: Air Handler 2
Duration: 8 hours
Reason: 
We request bldg 32-AH2 shutdown (affects Dreyfoos floors 4-9) and chilled water to the air handler 2 shutdown w/drain-down (affects 9th floor & roof) from 6 AM to 2 PM on Saturday, August 3rd, 2013 to install control wiring for control valves to the AH control panel and to disconnect chilled water piping & connect new chilled water off of the riser as part of the 32-roof repair project by Consigli Construction (508-458-0590).   Keith Diggans 4-6174 is the MIT project manager on behalf of Billy Homeyer.

Effect: 
Minimal loss of supply ventilation air (air handler 1 and 11 will still be running) and chilled water to the air handler unit #2 for the duration of the shutdown.

home help back first fref pref prev next nref lref last post