[171021] in Hotline Meeting
Bldg. 62 - 5th Floor; Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 25 15:30:06 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <cgilbert@MIT.EDU>, <billvit@MIT.EDU>
Date: Thu, 25 Jul 2013 15:29:59 -0400
Message-ID: <635B45552CD74E99A751A0574A2C93AE@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector shutdown notification for Bldg. 62, 5th floor on Monday, July 29 thru Wednesday August 14, 2013, from 6:00am-11:00pm, regular work days, is for your information. No response is required to this notification. Any questions please contact Billy Homeyer X.8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
Type: Normal
Date: July 29, 2013
Day: Monday
Time: 6:00am -11:00pm
Building(s): 62
Room(s): 5th floor
System: Smoke detectors
Duration: 17 hours
Reason:
Demolition of plaster ceiling, construction dust.
Effect:
Loss of smoke detector coverage in area during duration of shutdown.