[171019] in Hotline Meeting
*Extended* Bldg.W34-1st & 2nd Floor Mechanical Space Smoke Detector
daemon@ATHENA.MIT.EDU (Jessica Westgate)
Thu Jul 25 13:49:41 2013
From: Jessica Westgate <jwestgat@plant.mit.edu>
To: "shutdown-response@mit.edu" <shutdown-response@mit.edu>,
"undisclosed_recipients@mit.edu" <undisclosed_recipients@mit.edu>,
"elder@MIT.EDU" <elder@mit.edu>, "heinl@mit.edu" <heinl@mit.edu>,
"chouston@mit.edu" <chouston@mit.edu>, "slett@mit.edu" <slett@mit.edu>,
"djmartin@mit.edu" <djmartin@mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
Ops RM Fire Protection Team
<rm-fire-prot-team@mit.edu>,
Karen Semerjian <ksemerj@plant.mit.edu>
CC: "jwestgat@mit.edu" <jwestgat@mit.edu>,
Jack Mannion
<JMannion@plant.mit.edu>
Date: Thu, 25 Jul 2013 13:49:34 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C63A8A9D@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *Extended* Smoke Detector, shutdown notification for Bldg.W34-1st & 2nd Floor Mech. Spaces on *Friday, July 26, 2013 6:00am-3:00pm* is for your information. No response required to this notification. Any question please contact Bill Radochia 3-6361.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Jessica Westgate
Operations Center
Type: Normal
Date: July 26, 2013
Day: Monday
Time: 6:00am-3:00pm
Building(s): W34
Room(s): 1st & 2nd Floor Mechanical Spaces
System: Smoke Detectors
Duration: 9 hours/day
Reason: Welding
Effect: Loss of smoke detectors in area during the duration of the shutdown.