Approved - Bldg. 1 - All, Fire Alarm Testing w/live audible shutdown

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Tue Jul 23 14:39:16 2013

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "mbuehler@MIT.EDU" <mbuehler@mit.edu>,
        "patdixon@mit.edu"
	<patdixon@mit.edu>,
        "jgermain@mit.edu" <jgermain@mit.edu>,
        "ghavidel@MIT.EDU"
	<ghavidel@mit.edu>,
        "savicki@mit.edu" <savicki@mit.edu>,
        "OPS RM Campus
 Services Main" <rm-mcs@mit.edu>,
        "sbghosh@MIT.EDU" <sbghosh@mit.edu>, "fenner@mit.edu" <fenner@mit.edu>,
        MIT Schedules Office <schedules@mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>, "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@mit.edu>,
        "Ops RM Shutdown" <rm-shutdown@mit.edu>,
        William Radochia
	<wradochi@plant.mit.edu>
Date: Tue, 23 Jul 2013 14:39:10 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C625051A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Fire Alarm Testing w/live audible shutdown for Bldg. 1-All starting at 11:00pm on Tuesday, July 23, 2013  through 7:00am on Wednesday, July 24, 2013 is for your information. 

Any questions please contact Billy Homeyer x8-0432.


Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request a bldg 1-all fire alarm shutdown from 11 PM on Tuesday, July 23rd (tonight) to 7 AM on Wednesday, July 24th, 2013 for J. & M. Brown Co. (Wayne Maginnis 617-212-2059) to switchover 5 existing pull stations to the new Simplex system and to conduct *live audible 1st party testing of the new bldg 1 fire alarm system* as part of the bldg 1 life-safety upgrades project by Tishman Construction (Dennis Ryan 617-594-0664). Brian Healy 8-8565 is the MIT project manager.

Type: Normal
Date: July 23, 2013
Day: Tuesday
Time: 11:00pm (tues) - 7:00am (wed)
Building(s): Bldg. 1
Room(s): All
System: Fire Alarm Testing w/live audible
Duration: 8hrs
Reason: 
switchover five existing pull stations to the new fire alarm system and live test

Effect: 
Loss of Fire Alarms during the shutdown.
 