[170923] in Hotline Meeting
Approved - Bldg. E25 - Normal Emergency Power and Emergency Power
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Mon Jul 22 13:42:19 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
"craigp@MIT.EDU" <craigp@mit.edu>,
"OPS RM Campus Services East" <rm-ecs@mit.edu>,
Ops Custodial Admin & Support
Staff <cust-staff@mit.edu>,
"adaz@mit.edu" <adaz@mit.edu>, "bengel@mit.edu"
<bengel@mit.edu>,
"rdfadel@MIT.EDU" <rdfadel@mit.edu>,
"tquinn@mit.edu"
<tquinn@mit.edu>, "ninadm@mit.edu" <ninadm@mit.edu>,
Michael Smith
<masmith@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"MIT Schedules
Office" <schedules@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>,
Steven Gilligan <sgilliga@plant.mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>
Date: Mon, 22 Jul 2013 13:42:11 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C624FE80@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Normal Emergency Power and Emergency Power Panel ELR-R Shutdown is for bldg. E25 - on Tuesday, July 23, 2013 from 3:00am til 6:00am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x-3-0220
Type: Normal
Date: July 23, 2013
Day: Tuesday
Time: 3:00am - 6:00am
Building(s): E23
Room(s): all
System: emergency/building power
Duration: 3:00am - 6:00am
Reason:
We request a bldg E25 normal emergency power shutdown, 480V emergency panel ELR-R, located in the penthouse and serving stairwell pressurization fans and EF86, from 3 AM to 6 AM on Tuesday morning, July 23rd, 2013 for EG Sawyer Electric (Ed Murphy 781-974-0679) to install two 25A circuit breakers and tie-in new exhaust fans that will serve the cleanroom for the E25-6th floor Prof McGee Lab project by DC Beane (Ryan Kucinski 617-997-9498). Paul Murphy 4-6163 and Biss Teelucksingh 2-5972 are the MIT project managers.
Panel ELR-R serves stairwell pressurization fans 1 and 2 (normally off) and EF86 is the E23/E25 atrium exhaust fan.
Effect:
Loss of normal emergency power for the duration of this shutdown.