RE: Bldg.46-1st floor/loading dock area Smoke Detector Shutdown

daemon@ATHENA.MIT.EDU (Jessica Westgate)
Mon Jul 22 10:18:11 2013

From: Jessica Westgate <jwestgat@plant.mit.edu>
To: "shutdown-response@mit.edu" <shutdown-response@mit.edu>,
        "undisclosed_recipients@mit.edu" <undisclosed_recipients@mit.edu>,
        "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
        Gerry Desmond
	<gdesmond@mit.edu>, "handsom@MIT.EDU" <handsom@mit.edu>,
        "hegarty@mit.edu"
	<hegarty@mit.edu>,
        "rqsmith@mit.edu" <rqsmith@mit.edu>,
        "bbrown@mit.edu"
	<bbrown@mit.edu>,
        "cgallo34@mit.edu" <cgallo34@mit.edu>,
        "jstatile@mit.edu"
	<jstatile@mit.edu>,
        "macdonaj@mit.edu" <macdonaj@mit.edu>,
        "rmarini@mit.edu"
	<rmarini@mit.edu>,
        "mmpatt@mit.edu" <mmpatt@mit.edu>,
        "OPS RM Campus
 Services Main" <rm-mcs@mit.edu>,
        Ops CSG All <csg-all@mit.edu>, "gwolf@mit.edu" <gwolf@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "liberman@mit.edu" <liberman@mit.edu>,
        "heatherg@mit.edu" <heatherg@mit.edu>,
        "k_brown@MIT.EDU" <k_brown@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF Customer Service Center"
	<dof-csc@mit.edu>,
        Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
        Karen Semerjian <ksemerj@plant.mit.edu>
CC: "jwestgat@mit.edu" <jwestgat@mit.edu>, "sudy@mit.edu" <sudy@mit.edu>
Date: Mon, 22 Jul 2013 10:17:29 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C624FC52@dof-exchmbx01.facilities.ms.mit.edu>
In-Reply-To: <89B619635EF14A0385ADD85D7FDFCDFC@facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

This shutdown has been cancelled for Tuesday, July 23, 2013 and will resume on Wednesday, July 24, 2013. Any questions please contact Billy Homeyer 8-0432.

-----Original Message-----
From: shutdown-response@mit.edu [mailto:shutdown-response@mit.edu] 
Sent: Friday, June 28, 2013 11:00 AM
To: undisclosed_recipients@mit.edu
Cc: jwestgat@mit.edu; sudy@mit.edu
Subject: Bldg.46-1st floor/loading dock area Smoke Detector Shutdown Notification
Importance: High

The following Smoke Detector, shutdown notification for Bldg.46-1st floor/loading dock area on Monday, July 1, 2013 through Friday, July 26, 2013 (regular work days only and excluding MIT holiday) from 6:00am-2:00pm is for your information. No response required to this notification. Any question please contact Billy Homeyer 8-0432. 

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Jessica Westgate
Operations Center

Type: Normal
Date: July 1, 2013
Day: Monday
Time: 6:00am-200pm
Building(s): 46
Room(s): 1st floor/loading dock area
System: Smoke Detectors
Duration: 8 hours/day
Reason: 
For construction dust and all general construction-related activities.

Effect: 
Loss of smoke detectors in area during the duration of the shutdown. 