[170770] in Hotline Meeting
Approved - Bldg. W20-2nd and 3rd fl. Air Handler #6 Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Tue Jul 16 14:39:44 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "mwf@mit.edu" <mwf@mit.edu>, "liscott@mit.edu" <liscott@mit.edu>,
"tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"sdimond@mit.edu" <sdimond@mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"ois-plant-notify@mit.edu" <ois-plant-notify@mit.edu>,
"lsc-chairman@mit.edu" <lsc-chairman@mit.edu>,
"lsc@mit.edu" <lsc@mit.edu>, "mreagan@mit.edu" <mreagan@mit.edu>,
"lrbrutti@mit.edu" <lrbrutti@mit.edu>, "rcruz@mit.edu" <rcruz@mit.edu>,
"semo-admin@mit.edu" <semo-admin@mit.edu>,
"tenman@the-tech.mit.edu" <tenman@the-tech.mit.edu>,
"shutdowns@the-tech.mit.edu" <shutdowns@the-tech.mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
"alegere@mit.edu" <alegere@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "sudy@mit.edu" <sudy@mit.edu>
Date: Tue, 16 Jul 2013 14:39:24 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C5F18CA2@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Air Handler #6 shutdown is for bldg. W20 - 2nd fl and 3rd fl (ventilation and interior cooling) (bsmt catering kitchen renovation project) is on Wednesday, July 17, 2013 from 6:00am - 7:30am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: July 17, 2013
Day: Wednesday
Time: 6:00am - 7:30am
Building(s): W20
Room(s): 2nd and 3rd fl.
System: supply ventilation,cooling
Duration: 1.5 hrs 6:00am - 7:30am
Reason:
We request a W20-AH6 shutdown from 6 AM to 7:30 AM on Wednesday morning July 17th, 2013 for relocating a small section of ductwork in the W20-458 mech room to make-way for a new supply fan installation as part of the W20-019 catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). Sudy Nally 8-8010 and Jason Mullen 4-7239 are the MIT project managers.
Effect:
Loss of supply ventilation and cooling for the duration of this shutdown.