Bldg. E25 - 6th Floor; Fire Protection Water, Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 11 14:06:02 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <cgilbert@MIT.EDU>, <biss@MIT.EDU>
Date: Thu, 11 Jul 2013 14:05:55 -0400
Message-ID: <EF97A727C8E44002B52CE5B5DA2D09F6@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire protection water shutdown notification for Bldg E25 - 6th foor, on Thursday, July 18th, and Monday, July 22nd, 2013, from 6:30am-2:30pm, is for your information. No response is required to this notification. Any questions please contact Billy Homeyer X.8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
The Safety Office will be advised of this and notify the Fire Department.
Type: Normal
Date: July 18, 2013
Day: Thursday
Time: 6:30am-2:30pm
Building(s): E25
Room(s): 6th floor
System: Fire Protection Water
Duration: 8 hours
Reason:
To relocate sprinkler heads.
Effect:
Loss of fire protection water in area during duration of shutdown.