[170641] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 32 - Floors 1 - 3, and Child Care - Exhaust Fan 17 Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 11 10:44:50 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggans@MIT.EDU>
Date: Thu, 11 Jul 2013 10:44:42 -0400
Message-ID: <8CDC445ABFDC424B9FAAA6A9E9B673CA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following exhaust fan 17 shutdown request for Bldg. 32 - Floors 1 - 3, and Child Care, on Monday, July 15, 2013, 5:00am - 8:00am, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: July 15, 2013
Day: Monday
Time: 5:00am - 8:00am 
Building(s): 32
Room(s): Floors 1 - 3 and Child Care
System: Exhaust Fan 17
Duration: 3 hours
Reason: 
We request a bldg 32-EF17 shutdown from 5 AM to 8 AM on Monday, July 15th, 2013 to relocate the rooftop toilet exhaust fan (NOTE: EF17 is the toilet exhaust fan for floors 1,2, 3 and includes the Child Care facility), as part of the 32-roof repair project by Consigli Construction (Carlin Grenier 508-458-0590).  Keith Diggans 4-6174 is the MIT project manager on behalf of Billy Homeyer.

Effect: 
Loss of toilet exhaust for the duration of the shutdown.

home help back first fref pref prev next nref lref last post