[170614] in Hotline Meeting
Bldg. W20-bsmt Normal 208V/120V Building Power Shutdown, W20 power panels PLK-A and B in rm 019
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jul 10 09:55:16 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sudy@MIT.EDU>
Date: Wed, 10 Jul 2013 09:54:57 -0400
Message-ID: <6EEAD7D06C36462E8BD7C508D21252D0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Normal 208V/120V Building Power Shutdown, W20 power panels PLK-A and B in rm 019 is for Bldg. W20 - basement on Wednesday, July 17, 2013 from 3:00AM - 7:00AM is for your information and approval. If you have any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: July 17, 2013
Day: Wednesday
Time: 3:00AM - 7:00AM
Building(s): W20
Room(s): basement/019
System: building power,condensate return
Duration: 3:00AM - 7:00AM
Reason:
We request a bldg W20-019 208V/120V power panels PLK-A and B, normal bldg power shutdown from 3 AM to 7 AM on Wednesday morning, July 17th, 2013 for A Murphy Electrical to temporarily refeed all loads out of this two tub panel in preparation for the installation of replacement panels as part of the W20-019 catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). Sudy Nally 8-8010 and Jason Mullen 4-7232 are the MIT project managers.
As of this writing, the only known effects of this shutdown outside of the W20-019/019A/019B construction area are alpine bagel, dough mixer alpine bagel, alpine bagel freezer and the steam recovery pump PM# 704808.
Effect:
Loss of building power to this area for the duration of this shutdown.