[170581] in Hotline Meeting
Bldg. W31 - All, fire protection water system, shutdown notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 8 12:07:29 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <wcutchin@MIT.EDU>, <Jcombs@MIT.EDU>
Date: Mon, 8 Jul 2013 12:07:25 -0400
Message-ID: <2DE43E6AAD6D4302821BDF5A4A7CC760@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Protection Water shutdown notification for Bldg W31 - All on Tuesday - Friday, 7/9-12/2013 from 6:00AM until 2:00PM, is for your information. No response is required to this notification. Any questions, please contact W Homeyer, ext 8-0432
We appreciate your patience while the repairs/renovations are in progress.
William Cutchin
Operations Center
Type: Normal
Date: July 9, 2012
Day: Tuesday
Time: 6:00AM until 2:00PM
Building(s): W31
Room(s): All
System: Fire Protection Water
Duration: 8 hours/day
Reason:
as a precautionary measure during demolition on the 3rd floor
Effect:
Loss of Fire Protection water in (building, floors, and/or rooms). The Safety office will be advised of this and notify the Fire Department.