[170554] in Hotline Meeting
Approved - Bldg. 38-All Fire Alarm (w/brief *live audible testing
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Fri Jul 5 08:11:16 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "achow@mit.edu" <achow@mit.edu>,
"fletch1@EECS.MIT.EDU"
<fletch1@EECS.MIT.EDU>,
"sbleeb@mit.edu" <sbleeb@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@mit.edu>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
"agallant@mit.edu"
<agallant@mit.edu>,
"airyan@MIT.EDU" <airyan@mit.edu>,
MIT Schedules Office
<schedules@mit.edu>,
"wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
"amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>,
"heatherg@mit.edu"
<heatherg@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
Gary Saffie <gsaffie@plant.mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
Eupremio Piccinonno
<Eupremio@plant.mit.edu>,
William H Radochia <wradochi@mit.edu>
Date: Fri, 5 Jul 2013 08:11:05 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C4820B20@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Fire Alarm Shutdown (w/brief *live audible testing prior to 9AM) is for Bldg. 38-all on Monday, July 8, 2013 from 6:00am - 9:00am is for your information. Any questions please contact Billy Homyer x8-0432.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938
Type: Normal
Date: July 8, 2013
Day: Monday
Time: 6:00am - 9:00am
Building(s): 38
Room(s): All
System: fire alarm
Duration: 6:00am - 9:00am
Reason:
We request a bldg 38-all fire alarm shutdown from 6 AM to 9 AM on Monday, July 8, 2013 for MacNichol Electric (Tom Durant 978-930-6001) to remove four speaker/strobes and relocate two temporarily to the ceiling within the 5th floor construction area. We will conduct a very brief *live audible test of the bldg 38 fire alarm system prior to 9 AM* in order to check the operation of the two remaining speaker/strobes and as part of the 38-5th floor renovation project by Acella Construction (Marcillio Silva 781-733-1248). Nicole Pisani 5-5157 and Biss Teelucksingh 2-5972 are the MIT project managers.
Effect:
Loss of fire alarm for the duration of this shutdown.