[170554] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved - Bldg. 38-All Fire Alarm (w/brief *live audible testing

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Fri Jul 5 08:11:16 2013

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "achow@mit.edu" <achow@mit.edu>,
        "fletch1@EECS.MIT.EDU"
	<fletch1@EECS.MIT.EDU>,
        "sbleeb@mit.edu" <sbleeb@mit.edu>,
        "OPS RM Campus
 Services Main" <rm-mcs@mit.edu>,
        "burkhart@mtl.mit.edu"
	<burkhart@mtl.mit.edu>,
        "diadiuk@mit.edu" <diadiuk@mit.edu>,
        "mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
        "agallant@mit.edu"
	<agallant@mit.edu>,
        "airyan@MIT.EDU" <airyan@mit.edu>,
        MIT Schedules Office
	<schedules@mit.edu>,
        "wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
        "amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "ksemerj@mit.edu" <ksemerj@mit.edu>,
        Gary Saffie <gsaffie@plant.mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "OPS RM Campus
 Services Main" <rm-mcs@mit.edu>,
        Eupremio Piccinonno
	<Eupremio@plant.mit.edu>,
        William H Radochia <wradochi@mit.edu>
Date: Fri, 5 Jul 2013 08:11:05 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C4820B20@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Fire Alarm Shutdown (w/brief *live audible testing prior to 9AM) is for Bldg. 38-all on Monday, July 8, 2013 from 6:00am - 9:00am is for your information.  Any questions please contact Billy Homyer x8-0432.

Thank you,

Bernadette Drinkwater
Repair and Maintenance
X3-0938

Type: Normal
Date: July 8, 2013
Day: Monday
Time: 6:00am - 9:00am
Building(s): 38
Room(s): All
System: fire alarm
Duration: 6:00am - 9:00am 
Reason: 
We request a bldg 38-all fire alarm shutdown from 6 AM to 9 AM on Monday, July 8, 2013 for MacNichol Electric (Tom Durant 978-930-6001) to remove four speaker/strobes and relocate two temporarily to the ceiling within the 5th floor construction area. We will conduct a very brief *live audible test of the bldg 38 fire alarm system prior to 9 AM* in order to check the operation of the two remaining speaker/strobes and as part of the 38-5th floor renovation project by Acella Construction (Marcillio Silva 781-733-1248). Nicole Pisani 5-5157 and Biss Teelucksingh 2-5972 are the MIT project managers.

Effect: 
Loss of fire alarm for the duration of this shutdown. 



home help back first fref pref prev next nref lref last post