Extended 2nd time - Bldg. 36-045 Smoke & Heat Detector Shutdown

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed Jul 3 08:16:39 2013

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
        MIT Schedules Office
	<schedules@mit.edu>,
        "wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
        "amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
        "mcweeney@mit.edu" <mcweeney@mit.edu>,
        William H Radochia <wradochi@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
Date: Wed, 3 Jul 2013 08:16:29 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C482065A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

This shutdown has been *Extended for a second time from Monday, July 8, 2013 - Friday, July 12, 2013. Any questions please contact Joe McWeeney x3-8731.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938


The following Smoke and Heat Detector shutdown notification for Bldg. 36- 045 on Wednesday, June, 26 - Friday, June 28, 2013 (Extended Monday, July 8, 2013 - Friday, July 12, 2013) is for your information. No response required to this notification. Any question please contact Joe McWeeney x3-8731.

We appreciate your patience while the repairs/renovations are in progress.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938


Type: Normal
Date: June 26, 2013
Day: Wednesday
Time: 7:30am - 3:30pm
Building(s): 36
Room(s): 045
System: Smoke and Heat Detectors
Duration: 8 hrs each day
Reason: 
Demolition of return fan RF8;grinding and cutting of metal

Effect: 
Loss of smoke detectors in area during the duration of the shutdown.
 


home help back first fref pref prev next nref lref last post