Bldg. 6C - All and Bldg. 4, Room 007 - Normal 208V Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jul 2 10:42:21 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mdeluga@MIT.EDU>
Date: Tue, 2 Jul 2013 10:41:34 -0400
Message-ID: <E02C5FE0E1E443D39A612296AC4F32DC@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following normal building power shutdown request for Bldg. 6C - All (normal lighting affected only), and Bldg. 4, Room 007 (temp loss of power to lab affected), on Tuesday, July 9, 2013, 2:00am - 6:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 9, 2013
Day: Tuesday
Time: 2:00am - 6:00am
Building(s): 6C and 4
Room(s): 6C - All and 4, Room 007
System: normal building power (temp loss of power to lab 4-007 and lighting only for 6C)
Duration: 4 hours
Reason:
We request a bldg 6C-208V normal power panel DPLIG1 shutdown from 2 AM to 6 AM on Tuesday morning, July 9th, 2013.
This panel is located in high voltage room 6C-0006AE and Bennett Electric (John Shaw 617-763-2840) needs to install a new 400A circuit breaker for back-up power the Prof Ceyer Lab on the 1st floors of bldg 2 and 6. This back-up power ties into a manual transfer switch in HV room 2-017E.
During this shutdown bldg 6C will be without normal lighting.
Lab 4-007 will temporarily go on generator power. Power panels A and B will both be powered and 4-007 will lose power only momentarily at the beginning and end of this shutdown.
This shutdown is being conducted as part of the bldg 2-Chemistry renovation project by Bond Brothers (Jesse Conklin 617-936-4175) and Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.
Panels fed out of DPLIG1 are 4-007 LPL4007A and B (DMSE Battery Lab) and 6C lighting panels LPL6G1, 2, 5, 6, 7, 8 and 9 - PLIG1, CPLI11, PLIG2, and CPLIG1.
Effect:
During this shutdown bldg 6C will be without normal lighting.
Lab 4-007 will temporarily go on generator power. Power panels A and B will both be powered and 4-007 will lose power only momentarily at the beginning and end of this shutdown.