[170474] in Hotline Meeting
Approved Bldg. 46 - All, Normal Building Power Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Mon Jul 1 13:12:03 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
"Gerry
Desmond" <gdesmond@mit.edu>,
"handsom@MIT.EDU" <handsom@mit.edu>,
"hegarty@mit.edu" <hegarty@mit.edu>,
"rqsmith@mit.edu" <rqsmith@mit.edu>, "bbrown@mit.edu" <bbrown@mit.edu>,
"cgallo34@mit.edu" <cgallo34@mit.edu>,
"jstatile@mit.edu" <jstatile@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>, "mmpatt@mit.edu" <mmpatt@mit.edu>,
"OPS
RM Campus Services Main" <rm-mcs@mit.edu>,
Ops CSG All <csg-all@mit.edu>, "gwolf@mit.edu" <gwolf@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"liberman@mit.edu" <liberman@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Electrical Controls Team
<rm-elecctl@mit.edu>,
"rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu"
<dcrovo@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "sudy@mit.edu" <sudy@mit.edu>
Date: Mon, 1 Jul 2013 13:11:51 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C481FC49@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved normal building power shutdown for Bldg. 46 - All, on Tuesday, July 2, 2013, 4:00am - 12:00pm and Wednesday, July 3, 2013, 4:00am - 6:00am, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: July 2, 2013
Day: Tuesday
Time: 4:00am - 12:00pm (7/2); 4:00am - 6:00am (7/3)
Building(s): 46
Room(s): All
System: Normal Building Power
Duration: 8 hours/2 hours
Reason:
We request bldg 46 normal bldg power shutdowns, 480V panel D42C1 located in 2148E from 4 AM to 12 noon on Tuesday, July 2nd for Suburban Electric (Don Ouellette 781-760-5422) to install 800A and 2A circuit breakers to serve the new MRI; and 480V panel D42C located in 2201u/m from 4 AM to 6 AM on Wednesday, July 3rd, 2013 to change out a 20A circuit breaker (fed a Leibert unit) to a 60A breaker in order to serve the new 1150 MRI room chiller and as part of the 46-1150 MRI Lab renovation project by Wise Construction (Chris Luongo 781-389-5749). Sudy Nally 8-8010 is the MIT project manager.
Panel D42C1 feeds panel L42C, rodent mag lab transformer, rodent mag lab humidifier, panel D22C, panel D21C, panel L41C and the rodent lab magnet transformer.
Panel D42C feeds lab vacuum pumps, lab and control air compressors, an animal bedding vacuum system, VFDs for pumps 5 and 6, CAC Leibert units 1-4, motor control center 2C, panel P22C and FCU 5.
Effect:
Loss of normal building power, heating hot water, chilled water, supply cooling air, compressed control air, compressed lab air, and lab vacuum for the duration of the shutdown.