[170425] in Hotline Meeting
Approved - Bldg. 13-All Fire Alarm (w/*live testing at 7AM) Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Wed Jun 26 14:51:34 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops Custodial Admin &
Support Staff" <cust-staff@mit.edu>,
"jbartels@MIT.EDU" <jbartels@mit.edu>,
"mbulsara@mit.edu" <mbulsara@mit.edu>,
"jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"jingkong@mit.edu" <jingkong@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
<dof-ehs@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>
Date: Wed, 26 Jun 2013 14:51:28 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C45904F7@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Fire Alarm (w/*live testing at 7AM) Shutdown is for bldg. 13-all on Thursday, June 27, 2013 from 6:00am - 8:00am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 27, 2013
Day: Thursday
Time: 6:00am - 8:00am
Building(s): 13
Room(s): All
System: fire alarm
Duration: 6:00am - 8:00am
Reason:
We request a bldg 13 fire alarm shutdown on Thursday, June 27th from 6 AM to 8 AM for MacNichol Electric, Simplex and Schneider Electric to replace defective 5104 toxic gas system battery charger hardware and modify the toxic gas alarm message and programming to signal general evacuation. We will conduct *live audible 1st/3rd party testing of the bldg 13 fire alarm system between 7 AM and 8 AM as part of the 5th floor Prof Allanore Lab renovation project by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.
Effect:
Loss of fire alarms for the duration of this shutdown.