[170405] in Hotline Meeting
Approved - Bldg. 6-All Exhaust Fan 1A,1B,1C and 1D; 3rd fl/4th fl
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Tue Jun 25 12:34:14 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"rjwilk@mit.edu" <rjwilk@mit.edu>, "galanek@mit.edu" <galanek@mit.edu>,
"bobk@mit.edu" <bobk@mit.edu>, "nmorriso@MIT.EDU" <nmorriso@mit.edu>,
"Paul
Lyons" <plyons@plant.mit.edu>,
OPS RM Campus Services Main <rm-mcs@mit.edu>,
Gerry Hughes <ghughes@mit.edu>, "Tarky@mit.edu" <Tarky@mit.edu>,
"khewitt@mit.edu" <khewitt@mit.edu>, "elsye@MIT.EDU" <elsye@mit.edu>,
"cmodica@mit.edu" <cmodica@mit.edu>, "morley@mit.edu" <morley@mit.edu>,
"MIT
Schedules Office" <schedules@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"jimwhite@MIT.EDU" <jimwhite@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"chibcha@MIT.EDU" <chibcha@mit.edu>, "zqueen@mit.edu" <zqueen@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
Warren Scott
<WScott@plant.mit.edu>,
"plyons@mit.edu" <plyons@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "mdeluga@mit.edu" <mdeluga@mit.edu>
Date: Tue, 25 Jun 2013 12:34:06 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C458FD54@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Exhaust Fan 1A, 1B, 1C and 1D: 3rd /4th fl make up air fan AH #4 is for bldg. 6-All on Tuesday, June 25, 2013 from 6:00pm til 6:00am on Wednesday, June 26, 2013 is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 25, 2013
Day: Tuesday
Time: 6:00pm (Tue) - 6:00am (Wed)
Building(s): 6
Room(s): all
System: exhaust fan, exhaust hoods
Duration: 6:00pm (Tue) - 6:00am (Wed)
Reason:
Dear all, I'd like to supplement this bldg 6 fume hood exhaust fans shutdown by adding 6-AH4 (3rd/4th floor make-up air) as part of our attempt to keep the bldg 6 building pressure negative to adjoining buildings, and the outside. MIT Instruments will make the actual call as to whether or not the fan must go down at 6 PM tomorrow night following the shutdown of the fume hood exhaust fans and evaluating bldg conditions. Both the shutdown form and work order 5193111 have been modified to reflect this addition.
Effect:
Loss of exhaust fan and exhaust hoods for the duration of this shutdown.