Bldg. 37-3rd fl. Normal Building Power Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jun 21 14:07:59 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Fri, 21 Jun 2013 14:07:52 -0400
Message-ID: <E930D757BFAE4FE7BD49BFB1F3F3DC18@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Building Power Shutdown is for bldg. 37 - 3rd fl. on Thursday, June 27, 2013 from 5:00am - 7:00am is for your information and approval.  Any questions please contact Steve Gilligan x3-8079.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: June 27, 2013
Day: Thursday
Time: 5:00am - 7:00am
Building(s): 37
Room(s): 3rd fl. random (fan coils 301/311, lights 310, recept. 301, 311, 315, 331
System: normal building power shutdown
Duration: 5:00am - 7:00am 2 hrs
Reason: 
This is to tie in new circuits for this area.

Effect: 
Loss of normal building power for the duration of this shutdown. 