[170348] in Hotline Meeting
Bldg. 38-All Fire Alarm Shutdown (w/a very brief live audible test between 7:30am and 9AM)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jun 21 13:03:57 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <pisanin@MIT.EDU>
Date: Fri, 21 Jun 2013 13:03:51 -0400
Message-ID: <0A8DD5FB1B0A4F3E8D4D7D5761FA6B09@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Alarm Shutdown (w/a very brief live audible test between 7:30am and 9:00am) is for bldg. 38-all on Wednesday, June 26, 2013 from 6:00am - 9:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 26, 2013
Day: Wednesday
Time: 6:00am - 9:00am
Building(s): 38
Room(s): all
System: fire alarm
Duration: 6:00am - 9:00am 3 hrs
Reason:
We request a bldg 38-all fire alarm shutdown from 6 AM to 9 AM on Wednesday, June 26th, 2013 for MacNichol Electric (Tom Durant 978-930-6001) and Simplex (Rich Perron 781-603-7799) to tie-in and program temporary 5th floor heat detectors (prior to sprinkler demo). We will conduct a very brief *live audible test of the bldg 38 fire alarm system* sometime between 7:30 and 9 AM as part of the bldg 38-5th floor CyPress Eng Design Studio renovation project by Acella Construction (Marcilio Silva 781-733-1248). Nicole Pisani 5-5157 and Biss Teelucksingh 2-5972 are the MIT project managers.
The brief *live test* will be announced over the fire alarm speakers as a test.
Effect:
Loss of fire alarms for the duration of this shutdown.