Bldg. 54- 131 and surrounding labs/offices - Building Power Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 20 09:39:32 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Thu, 20 Jun 2013 09:39:25 -0400
Message-ID: <9E4CC4B7A476411CA66CDE0A03739848@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following building power shutdown is for bldg. 54- 131 and surrounding labs/offices on Tuesday, June 25, 2013 from 5:00am- 7:00am is for your information and approval. Any questions please contact Steve Gilligan x3-8079.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: June 25, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): 54
Room(s): 131 - surrounding labs/office
System: building power, lights, computers, stairs/corridors, access controls
Duration: 5:00am - 7:00am 2 hrs
Reason: 
This is to wire circuit breakers into panel "PP-13-2".

Effect: 
Loss of building power, lights, computers and access controls for the duration of this shutdown. 