[170271] in Hotline Meeting

home help back first fref pref prev next nref lref last post

NEED APPROVAL - Bldg. 7 - All Fire Alarm (w/*live Audible testing 6/21, 225-27 between 6 and 7:30AM) Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jun 18 14:06:13 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <biss@MIT.EDU>
Date: Tue, 18 Jun 2013 14:06:06 -0400
Message-ID: <2416940E8B5244458D7A2DDB3C9F102B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Alarm (w/*live Audible testing 6/21, 25-27 between 6 and 7:30AM) Shutdown is for bldg. 7 - All fire alarm shutdown is on Thursday, June 19th through Thursday, June 26th as follows; from 6 AM to 2 PM on Thursday and Friday, June 20th and 21st. We will conduct *live audible 1st party testing between 6 AM to 7:30 AM on Fri. 6/21* and silent test until 2 PM; 

Then from 6 PM on Saturday, June 22nd to 7:30 AM on Tuesday, June 25th to conduct the transponder's 60 hour battery test and conduct a *continuous 15 minute live audible 3rd party test of the bldg 7-fire alarm system between 6 AM and 6:30 AM on Tuesday morning 6/25* followed by additional live audible 1st party testing until 7:30 AM* and silent test until 9 AM; 

and from 6 AM to 9 AM on Wednesday and Thursday, June 26th to conduct *live audible and silent 3rd party testing of the bldg 7 fire alarm system* . We will *live test between 6 AM and 7:30 AM on Wed., June 26, 2013 and Thursday, June 27, 2013 and this is for your information and approval.

Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: June 21, 2013
Day: Thursday
Time: multiple days and times please see description reason.
Building(s): 7
Room(s): all
System: fire alarm
Duration: 7 days
Reason: 
We request bldg 7-all fire alarm shutdowns on Thursday, June 19th through Thursday, June 26th as follows; from 6 AM to 2 PM on Thursday and Friday, June 20th and 21st for Simplex (Rich Perron 781-603-7799)/MacNichol Electric (Mike Bryson 781-760-7416) tie tie-in, program and 1st party test new 7-304 fire alarm devices and a Simplex transponder. We will conduct *live audible 1st party testing between 6 AM to 7:30 AM on Fri. 6/21* and silent test until 2 PM; 

from 6 PM on Saturday, June 22nd to 7:30 AM on Tuesday, June 25th to conduct the transponder's 60 hour battery test and conduct a *continuous 15 minute live audible 3rd party test of the bldg 7-fire alarm system between 6 AM and 6:30 AM on Tuesday morning 6/25* followed by additional live audible 1st party testing until 7:30 AM* and silent test until 9 AM; 

and from 6 AM to 9 AM on Wednesday and Thursday, June 26th to conduct *live audible and silent 3rd party testing of the bldg 7 fire alarm system* to be witnessed by DEI Systems (Phil Deneault 508-341-4184). We will *live test between 6 AM and 7:30 AM on Wed., Thurs. 6/26 and 27* 

and all as part of the 7-304 Architecture offices project by Renovations Inc. (Jim Abbisso 617-594-7650). Biss Teelucksingh 2-5972 is the MIT project manager.
*live testing scheduled simplified*
Fri 6/21 6-7:30AM Simplex; MacNichol
Tues 6/25 6-7:30AM DEI, Simplex, MacNichol
Wed/Thurs 6/26,27 DEI, MacNichol

MIT Fire will cut power to the new transponder Saturday evening 6/22 at 6 PM and bldg 7 will display loss of AC power trouble until Tuesday morning 6/25. 



Effect: 
Loss of fire alarms for the duration of this shutdown. 

home help back first fref pref prev next nref lref last post