[170214] in Hotline Meeting
*Extended and Modified - Bldg. 32 - Gates, Floors 4 through 9 - Normal Building Power and Air Handler 3 Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 17 12:19:48 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggins@MIT.EDU>
Date: Mon, 17 Jun 2013 12:19:33 -0400
Message-ID: <03B1F750A744469D8615231D3FB31342@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following *extended and modified normal building power and air handler 3 shutdown request for Bldg. 32 - Gates, Floors 4 through 9, on Tuesday, June 18, 2013, 5:00am - 7:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 18, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): 32
Room(s): Gates, Floors 4 through 9
System: Normal Building Power and Air Handler 3
Duration: 2 hours
Reason:
Original request: We request a brief 32-Gates AH3 shutdown (serves floors 4 thru 9 Gates) from 6 AM to 7 AM on Tuesday morning, June 11th, 2013 to tie-in temporary power for the 32 roof repair project out of 32G-949E 208V/120V power panel M2GP. M2GP serves AH3 auxiliaries; VFD housing heatpump and fan coil unit. AH3 will probably not need to be shutdown during this power panel shutdown but I see it best to request the shutdown none the less. Consigli Construction contact/super is Carlin Grenier 508-509-2935, thank you, Billy Homeyer 8-0432
*Extended/Modified Request - We would like to extend and modify the 32-Gates AH3 (serves floor 4 thru 9 Gates) normal power shutdown from 5 AM to 7 AM on Tuesday morning, June 25th, 2013 to install a permanent 50 amp breaker for a welding outlet that is being installed on the roof out of 32G-949 208V/120V power panel M2GP. M2GP serves AH3 auxiliaries; VFD housing heatpump and fan coil unit as part the 32-roof repair project by Consigli Construction (Carlin Grenier 508-509-2935. Keith Diggans 4-6174 and John Engle 4-5001 are the MIT project managers on behalf of Billy Homeyer.
Effect:
Loss of normal building power, and supply ventilation and cooling air for the duration of the shutdown.