Bldg. E23-all Fire Alarm (w/*live audible testing 9:00PM - 5:00AM)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 17 09:23:05 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <biss@MIT.EDU>
Date: Mon, 17 Jun 2013 09:23:00 -0400
Message-ID: <FBF741789373461BAF7447A1DC7742F4@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Alarm (w/*live audible testing 9:00PM - 5:00AM) is for bldg. E23 - All on Thursday, June 20, 2013 from 9:00pm - Friday, June 2,1 2013 at 5:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 20, 2013
Day: Thursday
Time: 9:00PM (Thu) - 5:00AM (Fri)
Building(s): E23
Room(s): All
System: fire alarm
Duration: 9:00PM (Thu) - 5:00AM (Fri)
Reason:
We request a bldg E23 fire alarm shutdown from 9 PM on Thursday evening, June 20th to 5 AM on Friday, June 21st, 2013 to conduct 3rd party testing of the bldg E23 fire alarm system (to be witnessed by J. & M. Brown Co. - Wayne Maginnis 617-212-2059). We will conduct intermittent *live audible testing of the bldg E23 fire alarm system between 11 PM and 5 AM* as part of the E23 Pharmacy storefront project by Elaine Construction (Bernie Cincotta 617-590-3944). Biss Teelucksingh 2-5972 and Kim Sutherland 8-5962 are the MIT project managers.
Also; MIT Sprinkler required to flow water at 11 PM.
Effect:
Loss of fire alarms for the duration of this shutdown.