[170126] in Hotline Meeting
*Revised - Bldg. W35 - All, Normal Building Power (208V/120V)
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jun 12 12:59:19 2013
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "elder@MIT.EDU" <elder@mit.edu>, "djmartin@mit.edu" <djmartin@mit.edu>,
"tmertz@mit.edu" <tmertz@mit.edu>, Ops CSG All <csg-all@mit.edu>,
"OPS RM
Campus Services West" <rm-wcs@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Ops RM Electrical Controls Team <rm-elecctl@mit.edu>,
"rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu" <dcrovo@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
Ops RM Support Staff <rm-support@mit.edu>
CC: "janb@mit.edu" <janb@mit.edu>
Date: Wed, 12 Jun 2013 12:59:14 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C3A83001@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *revised normal building power (208V/120V) shutdown request for Bldg. W35 - All, on Friday, June 14, 2013, 12:01am - 5:30am, is being amended to add some emergency power to be shutdown from 4:30am - 5:30am as described below, and is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 14, 2013
Day: Friday
Time: 12:01am - 5:30am
Building(s): W35
Room(s): All
System: Normal Building Power (208V/120V) and some emergency power from 4:30am - 5:30am
Duration: 5-1/2 hours
Reason:
We request a bldg W35-all normal bldg power shutdown, all 208V/120V normal power from 12:01AM to 5:30 AM on Friday morning, June 14th, 2013 for MacNichol Electric to install a 100A circuit breaker in panel DPH2 (located in 228E), run the new conduit and break into panel for the new scoreboard power feed as part of the W35 scoreboard replacement project by Barr and Barr Builders (John Bidgood 508-686-0870). Jan Burke 8-5463 and Alex Campbell 617-939-8836
*Revised - Dear all, I'd like to amend this shutdown by adding some emergency power to it for 4:30 AM to 5:30 AM. We need to install a 20A circuit breaker in emergency power panel APLEM3 for the new scoreboard maintenance lift. 3rd floor emergency power electric room panels APLEM3 and APLEM3-1 need to be shutdown via the 480V EP feed to the 480V-208V transformer.
Effect:
Effect of this shutdown is all mechanical/office/athletic equipment in W35 not on emergency power.
The following will be affected during the 1 hour Emergency Power shutdown:
Main pool lights
Security (has 6 hour battery back-up) and
Secure access doors
Exhaust fan 9
ATC panel (auto temp control)
Tel/data
Electric doors
Elevator shunt trip
Fire alarm (60 hour battery back-up) goes into trouble condition loss of a/c power