[170048] in Hotline Meeting
Bldg. W35 - All, Normal Building Power (208V/120V) Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jun 11 08:55:59 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <janb@MIT.EDU>
Date: Tue, 11 Jun 2013 08:55:55 -0400
Message-ID: <93EE9AB8B9344BC79B305834E0625F5B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following normal building power (208V/120V) shutdown request for Bldg. W35 - All, on Friday, June 14, 2013, 12:01am - 5:30am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 14, 2013
Day: Friday
Time: 12:01am - 5:30am
Building(s): W35
Room(s): All
System: Normal Building Power (208V/120V)
Duration: 5-1/2 hours
Reason:
We request a bldg W35-all normal bldg power shutdown, all 208V/120V normal power from 12:01AM to 5:30 AM on Friday morning, June 14th, 2013 for MacNichol Electric to install a 100A circuit breaker in panel DPH2 (located in 228E), run the new conduit and break into panel for the new scoreboard power feed as part of the W35 scoreboard replacement project by Barr and Barr Builders (John Bidgood 508-686-0870). Jan Burke 8-5463 and Alex Campbell 617-939-8836
Effect:
Effect of this shutdown is all mechanical/office/athletic equipment in W35 not on emergency power.