[170037] in Hotline Meeting
Bldg.E25-6th floor Fire Protection Water Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 10 14:03:21 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jwestgat@MIT.EDU>, <biss@MIT.EDU>
Date: Mon, 10 Jun 2013 14:03:11 -0400
Message-ID: <C6A2F42119CF499EA9F03C5D63C0BBD0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fire Protection Water, shutdown notification for Bldg.E25-6th floor on Tuesday, June 11, 2013 from 6:00am-2:00pm is for your information. No response required to this notification. Any question please contact Billy Homeyer 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Jessica Westgate
Operations Center
The Safety Office will be advised of this and notify the Fire Department.
Type: Normal
Date: June 11, 2013
Day: Tuesday
Time: 6:00am-2:00pm
Building(s): E25
Room(s): 6th floor
System: Fire Protection Water
Duration: 8 hours
Reason:
To reconfigure 6th floor construction area branchline piping, install 2 additional heads.
Effect:
Loss of fire protection water in area during the duration of the shutdown.