NEED APPROVAL - Bldg. 32 - Normal Power Panel M2GP Shutdown for Air Handler #3 (feeds AH3 heatpump and fan coil unit) Gates floors 4 thru 9

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 10 12:56:31 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <kdiggins@MIT.EDU>
Date: Mon, 10 Jun 2013 12:56:20 -0400
Message-ID: <E3A67520062449998A284C0413E4371F@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Power Panel M2GP Shutdown for Air Handler #3 (feeds AH3 heatpump and fan coil unit) is for bldg. 32 - Gates floors 4 thru 9 is on Tuesday, June 11, 2013 from 6:00am - 7:00am is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval. 


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Critical
Date: June 11, 2013
Day: Tuesday
Time: 6:00am - 7:00am
Building(s): 32 Gates Tower
Room(s): 4th fl thru 9th fl
System: building power, supply ventilation, cooling, air handler #3
Duration: 6:00am - 7:00am 1 hr.
Reason: 
We request a brief 32-Gates AH3 shutdown (serves floors 4 thru 9 Gates) from 6 AM to 7 AM on Tuesday morning, June 11th, 2013 to tie-in temporary power for the 32 roof repair project out of 32G-949E 208V/120V power panel M2GP. M2GP serves AH3 auxiliaries; VFD housing heatpump and fan coil unit. AH3 will probably not need to be shutdown during this power panel shutdown but I see it best to request the shutdown none the less. Consigli Construction contact/super is Carlin Grenier 508-509-2935, thank you, Billy Homeyer 8-0432



Effect: 
Loss of normal building power, supply ventilation, cooling, air handler #3 for the duration of this shutdown. 