[170031] in Hotline Meeting
Approved - Bldg. 54 - rm 511 - Normal Building Power Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Mon Jun 10 07:21:11 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"craigp@MIT.EDU" <craigp@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
"w1mx-officers@mit.edu" <w1mx-officers@mit.edu>,
"MIT
Schedules Office" <schedules@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
"sgilliga@mit.edu"
<sgilliga@mit.edu>
Date: Mon, 10 Jun 2013 07:21:02 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C2EEA353@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Normal Building Power Shutdown is for bldg. 54 - rm 511 is on Tuesday, June 11, 2013 from 5:00am - 7:00am is for your information. Any questions please contact Steve Gilligan x3-8079.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 11, 2013
Day: Tuesday
Time: 5;00am - 7:00am
Building(s): 54
Room(s): 511
System: normal building power
Duration: 5:00am - 7:00am
Reason:
This is to remove old circuits within this space.
Effect:
Loss of normal building power for the duration of this shutdown.