[170015] in Hotline Meeting
Emergency Bldg. 32 - Air Handler 3 Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jun 7 11:42:08 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mdmobley@MIT.EDU>, <rcarr@MIT.EDU>
Date: Fri, 7 Jun 2013 11:41:56 -0400
Message-ID: <16678087EA2540D9AA250E259027A8D7@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following emergency air handler 3 shutdown notification for Bldg. 32 on Friday, June 7, 2013, 11:30am - until repairs are complete (approximately 3:00pm), is for your information. Any questions, please contact Mike Mobley, x4-4556.
We apologize for any inconvenience this may cause you.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Emergency
Date: June 7, 2013
Day: Friday
Time: 1130am - until repairs are complete (approximately 3pm)
Building(s): 32
Room(s): -
System: Air Handler 3
Duration: until repairs are complete
Reason:
inspection of unit for bad bearings thought to be the cause of the unit vibrating - prevention of further damage to the unit.
Effect:
Loss of supply ventilation, cooling, and heating air for the duration of the shutdown.