Approved Bldg. 6C - 2nd Floor, Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Mon Jun 3 12:28:39 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
        Ops CSG All
	<csg-all@mit.edu>, "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "morley@mit.edu"
	<morley@mit.edu>,
        "momeara@mit.edu" <momeara@mit.edu>,
        "chibcha@MIT.EDU"
	<chibcha@mit.edu>,
        "zqueen@mit.edu" <zqueen@mit.edu>,
        "k_brown@MIT.EDU"
	<k_brown@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "ajsilva@mit.edu" <ajsilva@mit.edu>, "mgodding@mit.edu" <mgodding@mit.edu>
Date: Mon, 3 Jun 2013 12:28:29 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C2671A54@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved chilled water shutdown for Bldg. 6C - 2nd Floor, on Wednesday, June 5, 2013, 7:00am - 2:00pm, is for your information.  Any questions, please contact Joe Silva, x3-1602.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: June 5, 2013
Day: Wednesday
Time: 7:00am - 2:00pm
Building(s): 6C
Room(s): 2nd Floor
System: Chilled Water
Duration: 7 hours
Reason: 
to repair a leak in the piping

Effect: 
Loss of chilled water and supply cooling air for the duration of the shutdown.