[169860] in Hotline Meeting
Bldg. 18 - 5th Floor - Process Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 31 09:40:32 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <ajsilva@MIT.EDU>, <mgodding@MIT.EDU>
Date: Fri, 31 May 2013 09:40:22 -0400
Message-ID: <9CD91AB6409E4939B63B4A04DEEE16DB@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following process chilled water shutdown request for Bldg. 18 - 5th Floor, on Tuesday, June 4, 2013, 7:00am - 2:00pm, is for your information and response. Any questions, please contact Joe Silva, x3-1602.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 4, 2013
Day: Tuesday
Time: 7:00am - 2:00pm
Building(s): 18
Room(s): 5th Floor
System: Process Chilled Water
Duration: 7 hours
Reason:
to inspect and clean strainer and install shut off valves
Effect:
Loss of process chilled water for the duration of the shutdown.