[169852] in Hotline Meeting
Approved - Bldg. 38-501,545,553,555,549, 547-comp. rm. and
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri May 31 09:18:13 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "achow@mit.edu" <achow@mit.edu>,
"fletch1@EECS.MIT.EDU"
<fletch1@EECS.MIT.EDU>,
"sbleeb@mit.edu" <sbleeb@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@mit.edu>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
"agallant@mit.edu"
<agallant@mit.edu>,
"airyan@MIT.EDU" <airyan@mit.edu>,
MIT Schedules Office
<schedules@mit.edu>,
"wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
"amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>,
"heatherg@mit.edu"
<heatherg@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
Steven Gilligan
<sgilliga@plant.mit.edu>
Date: Fri, 31 May 2013 09:18:04 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEF895B8@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Normal Building Power Shutdown is for Bldg. 38-501,545,553,555,549, 547-comp. rm. and surrounding areas is on Saturday, June 1, 2013 from 6:00am - 2:00pm is for your information. Any questions please contact Steve Gilligan x3-8079.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 1, 2013
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 38
Room(s): 501,545,553,555, 549, 547 - comp rm. surrounding areas
System: access controls, building power,computers, telephones, lighting, corridor/stairs
Duration: 6:00am - 2:00pm
Reason:
This shutdown is for a Make Safe for Abatement for this area.
Effect:
Loss of normal building power, access controls, building power,computers, telephones, lighting, corridor/stairs for the duration of this shutdown.