[169838] in Hotline Meeting
Approved - Bldg. W20 -019/019B kitchens - Air Handler #3
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Thu May 30 12:57:28 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: "mwf@mit.edu" <mwf@mit.edu>, "liscott@mit.edu" <liscott@mit.edu>,
"tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"sdimond@mit.edu" <sdimond@mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"ois-plant-notify@mit.edu" <ois-plant-notify@mit.edu>,
"lsc-chairman@mit.edu" <lsc-chairman@mit.edu>,
"lsc@mit.edu" <lsc@mit.edu>, "mreagan@mit.edu" <mreagan@mit.edu>,
"lrbrutti@mit.edu" <lrbrutti@mit.edu>, "rcruz@mit.edu" <rcruz@mit.edu>,
"semo-admin@mit.edu" <semo-admin@mit.edu>,
"tenman@the-tech.mit.edu" <tenman@the-tech.mit.edu>,
"shutdowns@the-tech.mit.edu" <shutdowns@the-tech.mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
"ksemerj@mit.edu" <ksemerj@mit.edu>,
Warren Scott
<WScott@plant.mit.edu>,
"alegere@mit.edu" <alegere@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "jcombs@mit.edu" <jcombs@mit.edu>
Date: Thu, 30 May 2013 12:57:07 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEF89153@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Air Handler #3 (PM#703527) Shutdown is for bldg. W20 - 019/019B (catering kitchen renovation project) starts on Friday, May 31, 2013 from 6:00am - until further notice (?mid August), is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 31, 2013
Day: Friday
Time: 6:00am - unitl further notice (?August)
Building(s): W20
Room(s): 019/019B kitchens
System: supply ventilation
Duration: 6:00am - until further notice (?August)
Reason:
We request a bldg W20-AH3 shutdown at 6 AM on Friday, May 31st, 2013 and until further notice (mid- August) as part of the W20-019/019B catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). AH3 serves the bsmt kitchen which is under construction and the fan located in mech rm W20-458 is going to be replaced. Sudy Nally 8-8010 and Jennifer Combs 3-7671 are the MIT project managers.
Effect:
Loss of supply ventilation for the duration of this shutdown.