Bldg. W20 -019/019B kitchens - Air Handler #3 (PM#703527) Shutdown (catering kitchen renovation project)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 29 14:03:44 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <jcombs@MIT.EDU>
Date: Wed, 29 May 2013 14:03:24 -0400
Message-ID: <1297B9FF80AF45EE8E159F0C5B4457F8@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Air Handler #3 (PM#703527) Shutdown is for bldg. W20 - 019/019B (catering kitchen renovation project) starts on Friday, May 31, 2013 from 6:00am - until further notice (?mid August), is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 31, 2013
Day: Friday
Time: 6:00am - unitl further notice (?August)
Building(s): W20
Room(s): 019/019B kitchens
System: supply ventilation
Duration: 6:00am - until further notice (?August)
Reason: 
We request a bldg W20-AH3 shutdown at 6 AM on Friday, May 31st, 2013 and until further notice (mid- August) as part of the W20-019/019B catering kitchen renovation project by Elaine Construction (Robin Lorscheider 781-727-8835). AH3 serves the bsmt kitchen which is under construction and the fan located in mech rm W20-458 is going to be replaced. Sudy Nally 8-8010 and Jennifer Combs 3-7671 are the MIT project managers.



Effect: 
Loss of supply ventilation for the duration of this shutdown. 