Approved - Bldg.39-301 East & Clean rooms, Fan Supply AH1, AH2,
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed May 29 12:51:15 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"domara@mit.edu"
<domara@mit.edu>, Jack Stark <jstark@plant.mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@mit.edu>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>, "mcweeney@mit.edu" <mcweeney@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops RM Shutdown" <rm-shutdown@mit.edu>,
Ops Custodial Admin & Support Staff
<cust-staff@mit.edu>
Date: Wed, 29 May 2013 12:51:06 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEE0A0A7@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Fan Supply AH1, AH2, shutdown for Bldg. 39-301 east & clean rooms on Saturday, June 1, 2013 is for your information. Any questions please contact Joe McWeeney x3-8731.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: June 1, 2013
Day: Saturday
Time: 7:00am - 11:00am
Building(s): 39
Room(s): 301 east & clean rooms
System: AH1, AH2
Duration: 4 hours
Reason:
Pre-Filter Change.
Effect:
Pre-Air Filters changes.