Revised - Bldg.39-301 east & clean rooms, Fan Supply AH1, AH2,
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed May 29 11:14:05 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@MIT.EDU>,
"domara@mit.edu"
<domara@MIT.EDU>, Jack Stark <jstark@plant.mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@MIT.EDU>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>
CC: "bdrink@mit.edu" <bdrink@MIT.EDU>, "mcweeney@mit.edu" <mcweeney@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>
Date: Wed, 29 May 2013 11:14:01 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEE09FA3@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
This has been revised from 7:00 -11:00am. AH1 & AH2.
Bernadette Drinkwater
Repair and Maintenance
X3-0938
-----Original Message-----
From: shutdown-response@mit.edu [mailto:shutdown-response@mit.edu]
Sent: Wednesday, May 29, 2013 11:02 AM
To: undisclosed_recipients@mit.edu
Cc: bdrink@mit.edu; mcweeney@mit.edu; shutdowns@mit.edu
Subject: Bldg.39-All, Fan Supply AH1, AH2, AH3, AH4 Shutdown Request
Importance: High
The following Fan Supply AH1, AH2, AH3, AH4 shutdown request for Bldg. 39-All on Saturday, June 1, 2013 is for your information and response. Any questions, please contact Joe McWeeney x3-8731.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: June 1, 2013
Day: Saturday
Time: 7:00am - 3:00pm
Building(s): 39
Room(s): All
System: AH1, AH2, AH3, AH4
Duration: 8 hours
Reason:
Pre-Filter Change.
Effect:
Pre-Air Filters changes. Only one fan at a time will be shutdown as filters are being changed.
This message was sent the following recipients: rm-mcs@mit.edu; domara@mit.edu; jstark@plant.mit.edu; burkhart@mtl.mit.edu; diadiuk@mit.edu; mcgrath@mtl.mit.edu;