Approved Bldg. 18 - Floors 1 through 5, PH1S North Lab - Air

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue May 28 09:27:10 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "jdoughty@mit.edu"
	<jdoughty@mit.edu>,
        "lippard@mit.edu" <lippard@mit.edu>, "swade@mit.edu"
	<swade@mit.edu>,
        "rjwilk@mit.edu" <rjwilk@mit.edu>,
        "OPS RM Campus Services
 East" <rm-ecs@mit.edu>,
        Ops CSG All <csg-all@mit.edu>, "gillooly@MIT.EDU"
	<gillooly@mit.edu>,
        "scottide@MIT.EDU" <scottide@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "k_brown@MIT.EDU" <k_brown@mit.edu>,
        "monaglek@MIT.EDU"
	<monaglek@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "ajsilva@mit.edu" <ajsilva@mit.edu>
Date: Tue, 28 May 2013 09:27:00 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEE09798@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved air handler 1, supply fan 5 #734089 shutdown for Bldg. 18 - Floors 1 through 5, PH1S North Lab, on Thursday, May 30, 2013, 7:00am - 8:00am, is for your information.  Any questions, please contact Joe Silva, x3-1602.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: May 30, 2013
Day: Thursday
Time: 7:00am - 8:00am
Building(s): 18
Room(s): Floors 1 through 5, PH1S North Lab - Rooms 063, 44, 05, 067, 050, 048
System: Air Handler 1, Supply Fan 5 #734089 
Duration: 1 hour
Reason: 
to investigate and repair if necessary a possible bad bearing

Effect: 
Loss of supply ventilation and cooling air for the duration of the shutdown.