[169711] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved Bldg. 18 - All, Reverse Osmosis/De-Ionized Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue May 28 09:18:32 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "jdoughty@mit.edu"
	<jdoughty@mit.edu>,
        "lippard@mit.edu" <lippard@mit.edu>, "swade@mit.edu"
	<swade@mit.edu>,
        "rjwilk@mit.edu" <rjwilk@mit.edu>,
        "OPS RM Campus Services
 East" <rm-ecs@mit.edu>,
        Ops CSG All <csg-all@mit.edu>, "gillooly@MIT.EDU"
	<gillooly@mit.edu>,
        "scottide@MIT.EDU" <scottide@mit.edu>,
        "heatherg@mit.edu"
	<heatherg@mit.edu>,
        "k_brown@MIT.EDU" <k_brown@mit.edu>,
        "monaglek@MIT.EDU"
	<monaglek@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "wscott@mit.edu" <wscott@mit.edu>
Date: Tue, 28 May 2013 09:18:25 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEE09773@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved reverse osmosis/de-ionized water shutdown for Bldg. 18 - All, on Wednesday, May 29, 2013, 6:00am - 10:00am, is for your information.  Any questions, please contact Warren Scott, x3-6328. 

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: May 29, 2013
Day: Wednesday
Time: 6:00am - 10:00am
Building(s): 18
Room(s): All
System: Reverse Osmosis/De-Ionized Water 
Duration: 4 hours
Reason: 
to repair several leaks in basement

Effect: 
Loss of de-ionized water for the duration of the shutdown.