[169695] in Hotline Meeting
Bldg. 46 - All, Fire Alarm Shutdown Notification and *Live Audible Testing Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 24 13:04:09 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sudy@MIT.EDU>
Date: Fri, 24 May 2013 13:04:05 -0400
Message-ID: <49052FA0C00048F281BB992FB2F9D158@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following fire alarm shutdown notification and *live audible testing request for Bldg. 46 - All, on Wednesday, May 29, 2013, 4:00am - 12:00pm and Thursday, May 30, 2013, 5:00am - 8:00am, with the *live audible testing taking place on Thursday, May 30, 2013, 5:00am - 8:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: May 29, 2013
Day: Wednesday
Time: 4:00am - 12:00pm (Wed.); 5:00am - 8:00am (Thurs.)
Building(s): 46
Room(s): All
System: Fire Alarm and *Live Audible Testing
Duration: 8 hours/3 hours
Reason:
We request bldg 46-all fire alarm shutdowns as follows; from 4 AM to 12 noon on Wednesday, May 29th for JMBCO (Tom Rose 617-799-7171) to relocate the addressable loop wiring conduits in 46-1150 to make-way for the RF shielded room; and from 5 AM to 8 AM on Thursday, May 30, 2013 to conduct *live audible testing of the bldg 46 fire alarm system* in order to test the remade riser wiring connections and as part of the bldg 46-1150 MRI Lab renovation project by Wise Construction (Chris Luongo 781-389-5749). Sudy Nally 8-8010 and Biss Teelucksingh 2-5972 are the MIT project managers.
Effect:
Loss of fire alarms for the duration of the shutdown and *live audible testing on Thursday.