Approved Bldg. 32D - 9th Floor Kitchen/Roof - Normal Building Power

daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri May 24 09:43:34 2013

From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Ops RM Electrical Controls Team
	<rm-elecctl@mit.edu>,
        "rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu"
	<dcrovo@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "ksemerj@mit.edu"
	<ksemerj@mit.edu>, "mwf@mit.edu" <mwf@mit.edu>,
        "liscott@mit.edu"
	<liscott@mit.edu>,
        "pwalsh@mit.edu" <pwalsh@mit.edu>, "kdonn@mit.edu"
	<kdonn@mit.edu>,
        "tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU"
	<myersm@mit.edu>,
        "jackc@csail.mit.edu" <jackc@csail.mit.edu>,
        "jon@csail.mit.edu" <jon@csail.mit.edu>,
        "steverug@CSAIL.MIT.EDU"
	<steverug@csail.mit.edu>,
        "lizaz@CSAIL.MIT.EDU" <lizaz@csail.mit.edu>,
        "zue@csail.mit.edu" <zue@csail.mit.edu>,
        "isabell@mit.edu" <isabell@mit.edu>, "sbleeb@mit.edu" <sbleeb@mit.edu>,
        Michael Fahie <mfahie@plant.mit.edu>,
        "OPS RM Campus Services Main" <rm-mcs@mit.edu>,
        "Martin O'Brien"
	<mobrien@plant.mit.edu>,
        "Stata-Custodial@mit.edu" <Stata-Custodial@mit.edu>,
        Ops CSG All <csg-all@mit.edu>, "dwright@MIT.EDU" <dwright@mit.edu>,
        "stata-desk@mit.edu" <stata-desk@mit.edu>,
        "dgeraci@mit.edu"
	<dgeraci@mit.edu>, "rosko@mit.edu" <rosko@mit.edu>,
        Michael Smith
	<masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
        "awolpert@mit.edu"
	<awolpert@mit.edu>, "edel@mit.edu" <edel@mit.edu>,
        "shanlon@mit.edu"
	<shanlon@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "lrbrutti@mit.edu"
	<lrbrutti@mit.edu>,
        "rcruz@mit.edu" <rcruz@mit.edu>, "aneely@mit.edu"
	<aneely@mit.edu>,
        "wayneb@mit.edu" <wayneb@mit.edu>,
        MIT Schedules Office
	<schedules@mit.edu>,
        "k_brown@MIT.EDU" <k_brown@mit.edu>,
        "monaglek@MIT.EDU"
	<monaglek@mit.edu>,
        "kdonaher@mit.edu" <kdonaher@mit.edu>,
        "kasabula@mit.edu"
	<kasabula@mit.edu>,
        "rpittari@mit.edu" <rpittari@mit.edu>,
        "ksimons@mit.edu"
	<ksimons@mit.edu>,
        "rwong@brighthorizons.com" <rwong@brighthorizons.com>,
        "dvorak@wi.mit.edu" <dvorak@wi.mit.edu>,
        "worklife@mit.edu"
	<worklife@mit.edu>
CC: "kdiggans@mit.edu" <kdiggans@mit.edu>
Date: Fri, 24 May 2013 09:42:48 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEC95ECC@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved normal building power (120/208V) shutdown for Bldg. 32D - 9th Floor Kitchen/Roof, on Tuesday, May 28, 2013, 5:00am - 7:00am, is for your information.  Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: May 28, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): 32 - Dreyfoos
Room(s): 9th Floor Kitchen/Roof
System: Normal Building Power (120/208V)
Duration: 2 hours
Reason: 
We request a bldg 32D-9thfl/roof normal 208V/120V bldg power shutdown, power panel M2D91 from 5 AM to 7 AM on Tuesday morning, May 28th, 2013 for the removal of a welding machine pigtail and the tie-in of temporary power for another phase of the 32 roof repairs project by Consigli Construction (Carlin Grenier 508-509-2935). Keith Diggans 4-6174 is the MIT project manager.

Effect: 
Loss of normal building power in the area designated, hall lighting, elevator machine room cooling, domestic hot water, and supply cooling air for the duration of the shutdown.