Bldg. 32D - 9th Floor Kitchen/Roof - Normal Building Power (120/208V) Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 22 13:13:19 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kdiggans@MIT.EDU>
Date: Wed, 22 May 2013 13:13:01 -0400
Message-ID: <AD62BEFE6ECF466FBB2A01794EE0F200@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following normal building power (120/208V) shutdown request for Bldg. 32D - 9th Floor Kitchen/Roof, on Tuesday, May 28, 2013, 5:00am - 7:00am, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: May 28, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): 32 - Dreyfoos
Room(s): 9th Floor Kitchen/Roof
System: Normal Building Power (120/208V)
Duration: 2 hours
Reason: 
We request a bldg 32D-9thfl/roof normal 208V/120V bldg power shutdown, power panel M2D91 from 5 AM to 7 AM on Tuesday morning, May 28th, 2013 for the removal of a welding machine pigtail and the tie-in of temporary power for another phase of the 32 roof repairs project by Consigli Construction (Carlin Grenier 508-509-2935). Keith Diggans 4-6174 is the MIT project manager.

Effect: 
Loss of normal building power in the area designated, hall lighting, elevator machine room cooling, domestic hot water, and supply cooling air for the duration of the shutdown.