[169534] in Hotline Meeting
Revised - Bldg. NW13-All Heating Hot Water & chilled water/process
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Wed May 22 07:13:00 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"craigp@MIT.EDU" <craigp@mit.edu>, "galanek@mit.edu" <galanek@mit.edu>,
"bobk@mit.edu" <bobk@mit.edu>, "wbm@mit.edu" <wbm@mit.edu>,
"nmorriso@MIT.EDU" <nmorriso@mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"pbrenton@MIT.EDU" <pbrenton@mit.edu>,
"censabel@MIT.EDU"
<censabel@mit.edu>,
"jpfoster@mit.edu" <jpfoster@mit.edu>,
"Eslau@mit.edu"
<Eslau@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"heatherg@mit.edu"
<heatherg@mit.edu>
CC: "bdrink@mit.edu" <bdrink@mit.edu>, "mmcorrei@mit.edu" <mmcorrei@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>
Date: Wed, 22 May 2013 07:12:55 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEC9503C@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
This shutdown has been revised to included chilled water/process chilled water along with heating hot water. Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0939
-----Original Message-----
From: shutdown-response@mit.edu [mailto:shutdown-response@mit.edu]
Sent: Tuesday, May 21, 2013 2:29 PM
To: undisclosed_recipients@mit.edu
Cc: bdrink@mit.edu; mmcorrei@mit.edu; shutdowns@mit.edu
Subject: Bldg. NW13-All Heating Hot Water shutdown request
Importance: High
The following heating hot water shutdown request for Bldg. NW13-All on Thursday, May 30, 2013 is for your information and response. Any questions please contact Mike Correirax8-9174.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: May 30, 2013
Day: Thursday
Time: 8:00am - 12:00pm
Building(s): NW13
Room(s): All
System: Heating Hot Water
Duration: 4 hours
Reason:
Chilled water change over system.
Effect:
Loss of cooling/heating/chilled/heating hot water