[169479] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 57 - All, Normal Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon May 20 12:40:52 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <ajsilva@MIT.EDU>, <rlucas@MIT.EDU>
Date: Mon, 20 May 2013 12:40:47 -0400
Message-ID: <F7300C41C5E148749F83975E69BD2C49@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following normal building power shutdown request for Bldg. 57 - All, on Thursday, May 23, 2013, 5:00am - 9:00am, is for your information and response.  Any questions, please contact Joe Silva, x3-1602.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-1602

Type: Normal
Date: May 23, 2013
Day: Thursday
Time: 5:00am - 9:00am
Building(s): 57
Room(s): All
System: Normal Building Power
Duration: 4 hours
Reason: 
repair 100 amp breaker in basement feed panel and perform preventive maintenance on switch gear

Effect: 
Loss of normal building power for the duration of the shutdown.