Approved - Bldg. E25-6th fl. (McGee Lab clean room) Chilled Water
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Mon May 20 09:23:43 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"jmganno@MIT.EDU" <jmganno@mit.edu>,
"macdonaj@mit.edu" <macdonaj@mit.edu>,
"craigp@MIT.EDU" <craigp@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"adaz@mit.edu" <adaz@mit.edu>, "bengel@mit.edu" <bengel@mit.edu>,
"rdfadel@MIT.EDU" <rdfadel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
"ninadm@mit.edu" <ninadm@mit.edu>, Michael Smith <masmith@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
MIT Schedules Office
<schedules@mit.edu>,
"scottide@MIT.EDU" <scottide@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"ksemerj@mit.edu"
<ksemerj@mit.edu>,
Warren Scott <WScott@plant.mit.edu>,
"plyons@mit.edu"
<plyons@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"Ops Custodial
Admin & Support Staff" <cust-staff@mit.edu>
Date: Mon, 20 May 2013 09:23:33 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEA9C599@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved - Chilled Water Shutdown is for bldg. E25 - 6th fl. (McGee Lab clean room) is on Tuesday, May 21, 2013 from 12:01(midnight) til 7:00am is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: May 21, 2013
Day: Tuesday
Time: 12:01am - 7:00am
Building(s): E25
Room(s): 6th fl.
System: chilled water, supply cooling
Duration: 12:01am - 7:00am
Reason:
Dear all, I'd like to reschedule this E25-6th floor chilled water shutdown to - Midnight (0000 hrs) to 7 AM (0700) on Tuesday morning, May 21st and still pending on our request for a local shutdown of power panel P26A3 for 15 minutes anytime prior for hooking up the welding machine. The effects of shutting off power to P26A3 are posted close to the very bottom of this mail. Both the shutdown form and work order 5814747 have been modified to reflect the new date of the chilled water shutdown, thanx, Billy H. 8-0432
Effect:
Loss of chilled water and supply cooling for the duration of this shutdown.