[169419] in Hotline Meeting
Approved - Bldg. 39 - rm. 328 Building Power Shutdown - (120V/208V)
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Mon May 20 09:03:53 2013
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"domara@mit.edu"
<domara@mit.edu>, Jack Stark <jstark@plant.mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@mit.edu>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
Steven Gilligan
<sgilliga@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>
Date: Mon, 20 May 2013 09:03:47 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEA9C556@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Building Power Shutdown is for Bldg. 39 - rm 328 - PL3 is on Wednesday, May 22, 2013 from 5:00am - 7:00am is for your information. Any questions please contact Steve Gilligan x3-8079.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
3-0938
Type: Normal
Date: May 22, 2013
Day: Wednesday
Time: 5:00am -7:00am
Building(s): 39
Room(s): 328
System: building power 120V/208V
Duration: 5:00am - 7:00am
Reason:
This is to install a new circuit.
Effect:
Loss of building power to area for duration of this shutdown.