Approved - Bldg. E23- Air Handler #11 - North end flrs , bsmt thru

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri May 17 12:19:09 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: OPS RM Campus Services East <rm-ecs@mit.edu>,
        "Ops Custodial Admin &
 Support Staff" <cust-staff@mit.edu>,
        "bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
        "brig@med.mit.edu" <brig@med.mit.edu>,
        "fris@med.mit.edu" <fris@med.mit.edu>,
        "heatherg@mit.edu" <heatherg@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "plyons@mit.edu" <plyons@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "ksemerj@mit.edu" <ksemerj@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "biss@mit.edu" <biss@mit.edu>
Date: Fri, 17 May 2013 12:19:03 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AEA9C0BA@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Air Handler #11 - North end flrs , bsmt thru 5 fl. (Pharmacy storefront project) is for bldg. E23 on Saturday, May 18, 2013 from 6:00am til Monday, May 20, 2013 at 6:00am is for your information.  Any questions please contact Billy Homeyer x8-0432.



Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 18, 2013
Day: Saturday
Time: 6:00am (Sat) til 6:00am (Mon)
Building(s): E23
Room(s): North End fls, bsmt thru 5th fl
System: supply ventilation, cooling
Duration: 6:00am (Sat) til 6:00am (Mon)
Reason: 
We request a bldg E23-AH11 shutdown (by the OPS Center) from 6 AM on Saturday morning, May 18th to 6 AM on Monday morning, May 20th, 2013 for the installation of medium pressure ductwork and VAV boxes off the main trunk of AH11 located behind the passenger elevator shaft in the Pediatrics Member Services area E23-191 and to allow time for the duct sealant to set and as part of the E23 Pharmacy storefront project by Elaine Construction (Bernie Cincotta 617-590-3944). Kim Sutherland 8-5962 and Biss Teelucksingh 2-5972 are the MIT project managers.

Effect: 
Loss of supply ventilation and cooling for the duration of this shutdown. 