[169400] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. N51-419 - Building Power Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 17 12:12:57 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@MIT.EDU>
Date: Fri, 17 May 2013 12:12:52 -0400
Message-ID: <2485AC762D9345D5977DFD30B378CC7D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Building Power Shutdown is for bldg. N51-419 is on Tuesday, May 21, 2013 from 5:00am - 7:00am is for your information and approval.  Any questions please contact Steve Gilligan x3-8079.


Would you please let us know if this does or does not have your approval. 


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 21, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): N51
Room(s): 419
System: building power, access panels, computers, telephones, lighting
Duration: 5:00am - 7:00am
Reason: 
This is to change over circuit breaker and receptacle in this space. 

Effect: 
Loss of building power, access panels, computers, telephones, lighting for the duration of this shutdown. 